Maemo.org Sprints/February 10

(Tasks: changing task status)
(Tasks)
Line 30: Line 30:
| 60%
| 60%
| Unfortunately more changes needed than expected, not completed yet
| Unfortunately more changes needed than expected, not completed yet
 +
|- style="background:LightBlue"
 +
| 9.09-10
 +
| Implement SSO sync-API endpoint for garage
 +
| Must
 +
| [http://maemo.org/profile/view/danielwilms/ danielwilms]
 +
| 80%
 +
| implemented new server instance for midgard account-sync, cas change from ldap to MySQL, certificates in place for endpoint-sync
|- style="background:LightBlue"
|- style="background:LightBlue"
| 9.11-08
| 9.11-08
Line 65: Line 72:
| 50%
| 50%
| Niels has been busy with server moves, and hasn't had a chance to talk to me this month. Ferenc will be documenting the server set-up during the move.
| Niels has been busy with server moves, and hasn't had a chance to talk to me this month. Ferenc will be documenting the server set-up during the move.
-
|- style="background:LightBlue"
 
-
| 9.09-10
 
-
| Implement SSO sync-API endpoint for garage
 
-
| Should
 
-
| [http://maemo.org/profile/view/danielwilms/ danielwilms]
 
-
| 80%
 
-
| implemented new server instance for midgard account-sync, cas change from ldap to MySQL, certificates in place for endpoint-sync
 
|- style=""
|- style=""
| 10.01-06
| 10.01-06

Revision as of 17:12, 2 February 2010

Contents

February 2010 Sprint planning

Tasks

Ongoing tasks carried here from the previous sprint + New tasks committed by their owners in the sprint meeting. They come from the tasks in the Backlog and the Proposals.

Completed Good progress Just standing Some help needed! Really stuck/delayed
Task ID Task Sprint priority Owner Percentage complete Notes
9.09-01 Push packaging policy updates Must X-Fade, danielwilms 60% Unfortunately more changes needed than expected, not completed yet
9.09-10 Implement SSO sync-API endpoint for garage Must danielwilms 80% implemented new server instance for midgard account-sync, cas change from ldap to MySQL, certificates in place for endpoint-sync
9.11-08 No orphaned pages and revise Wiki navigation Must dneary 80% See Maemowiki Action Group page for precise details, and Special:Lonelypages for progress.
9.12-01 Working bugzilla 3.4, migration path notes Must Andre, Karsten 80%
9.12-05 BMO: maemo.org custom features backport, Nokia patches Must Andre, Karsten 25%
9.12-07 BMO: CSS, maemo.org style Must Andre, Karsten 0%
10.01-03 Document processes for maemo.org infrastructure Must dneary 50% Niels has been busy with server moves, and hasn't had a chance to talk to me this month. Ferenc will be documenting the server set-up during the move.
10.01-06 Midgard & Midgard2 data sync Could indeyets 0% Implemented already, needs to be enabled and tested
10.01-07 Wiki & Midgard2 data sync Could danielwilms 0% Component of gforge can partly be reused
10.01-08 Enable CAS for Midgard Could indeyets 0%

Actions

None yet

Activity log

Latest activity report goes on top. Activity will be reported here, Qaiku #maemork channel (Atom feed) or talk.maemo.org.