May 2009 Sprint planning

Tasks

Ongoing tasks carried here from the previous sprint + New tasks committed by their owners in the sprint meeting. They come from the tasks in the Backlog and the Proposals.

Completed Good progress Just standing Some help needed! Really stuck/delayed
Task ID Task Sprint priority Owner Percentage complete Notes
8.11-01 Texts for maemo.nokia.com Must Quim 20%
9.02-01 List Maemo bugzilla patches - create patchset Must Andre 40%
9.06-01 Set up library.maemo.org environment Must dneary 0%
9.06-02 [[Talk:Git For Garage|Git For Garage - skin] Must Ferenc 0%
9.04-05 Implement new maemo.org layout and style - Bugzilla Must Andre 80%
9.04-07 Karma for applications - implement Should indeyets 60% Application-stats are gathered since 2009-06-10
9.04-08 ITP process/workflow around [1] Could jeremiah 90%
9.04-09 2009-04-06 May 09 Setup SSO testing environment Should Daniel ?
9.06-03 Further 20 packages through from Diablo Extras to Fremantle Extras Must Jeremiah 0%
9.06-04 Git For Garage - Conversion UI Should Ferenc 0%
9.05-05 Style and layout for MXR Could Ryan 20% Jaffa to contact Ryan about "VCS issues"
9.05-08 Brainstorm documentation Could Ryan 0%

Activity log

Latest activity report goes on top. Activity will be reported here, Qaiku or talk.maemo.org.