Task ID
| Task
| Sprint priority
| Owner
| Percentage complete
| Notes
|
9.08-01
| Get "Nokia patches" cleanly into Bugzilla .4 test install, dropping as many deltas as possible
| Must
| Ferenc
| 0%
|
9.08-02
| #3692 Re-import discussion karma
| Must
| Ferenc
| 50%
| The importer script is fixed and tested in the maemo-community list. 2668 post imported without a problem. The next import will be the latest mbox archive of developers list.
|
9.08-03
| Fix any other logged karma issues
| Must
| Ferenc
| 0%
| Will have to ping Niels to help me listing all outstanding issues.
|
9.06-05
| Package promotion/repository management/community QA interface
| Must
| X-Fade
| 90%
| Basic interface is in place, most tests look promising.
|
9.08-04
| Integrate minimae into package promotion to get infrastructure & UI in place
| Must
| Jeremiah
| 10%
| minimae in git
|
9.06-07
| Karma for applications - get agreement on formula
| Must
| indeyets
| 25%
| This sprint must: get data, come up with proposals, communicate to -community/developers and push for consensus.
|
9.07-01
| Setup SSO-integration (GForge)
| Must
| danielwilms
| 60%
|
|
9.08-05
| Identify/communicate to tmo users about upcoming election
| Must
| Jaffa
| 30%
| Account information received from X-Fade & Reggie. 1,600 users identified.
|
9.08-06
| Produce Maemo Summit 2009 budget v0.99
| Must
| qgil
| 0%
|
|
9.08-07
| Drive election process
| Must
| Jaffa
| 50%
| Initial announcements have been published.
|
9.08-08
| Co-ordinate summit council responsibilities
| Must
| timsamoff
| 0%
| Merchandising/accomodation etc.
|
9.08-09
| Promote summit & buzz/communication plan
| Must
| VDVsx
| 0%
|
|
9.08-10
| Draft quality guidelines for extras-testing to extras promotion
| Should
| qgil
| 10%
| Drafting at Extras-testing Quality_criteria + tmo discussion
|
9.06-12
| #4405: Task:Proof-read Human Interface Guidelines
| Should
| dneary
| 98%
| Merge upstream and ensure process in place so edits aren't lost
|
9.04-05
| Implement new maemo.org layout and style - Bugzilla
| Should
| Andre
| 80%
| Rough version in place.
|
9.08-11
| Document & communicate packages interface to testers
| Should
| Jaffa
| 0%
|
|
9.06-09
| Vendor Hardware Repositories - decide on sub-tasks for next sprint
| Should
| Stskeeps
| 0%
|
|
9.06-14
| Plan for the OMAP2 acceleration drivers
| Could
| qgil
| 10%
| Still blocked on TI contact.
|
9.08-12
| Improve reporting feed appearance on sprint page
| Could
| Ferenc
| 0%
| To liaise with Jaffa
|
9.04-08
| ITP process/workflow around prototype
| Could
| Jeremiah
| 90%
|
|