November 2009 Sprint planning

Tasks

Ongoing tasks carried here from the previous sprint + New tasks committed by their owners in the sprint meeting. They come from the tasks in the Backlog and the Proposals.

Completed Good progress Just standing Some help needed! Really stuck/delayed
Task ID Task Sprint priority Owner Percentage complete Notes
9.04-05 Implement new maemo.org layout and style - Bugzilla Must Andre, Karsten 80% Nokia surprised me by handing out devices at the Summit - hence bug reports got filed like mad => No progress here in October. Good news: Got Karsten back for a few hours per week for the rest of the year.
9.08-01 Document & communicate packages interface to testers Must Jaffa 0% Been blocked on 9.08-10, struggling to fit in time.
9.09-01 Push packaging policy updates Must X-Fade, danielwilms 40% Make some changes, waiting for Daniel to pass it to Nokia internal team.
9.10-03 Implement SSO backend Must indeyets 0%
9.10-04 Brainstorm: bug fixes and new features Must NetBlade 0% Related bug
9.10-05 Brainstorm: better categories view Must NetBlade 0%
9.10-06 Brainstorm: automoderation from sandbox to under consideration Must NetBlade 0%
9.10-07 Server migration Must Ferenc 0% Servers will be available in November only.
9.11-01 Refresh maemo.org intro Must qgil 0%
9.11-02 Maemo Greeters program Must texrat 0%
9.11-03 Get a decision on Developers should get karma based on the relevance of their software Must VDVsx 0%
9.11-04 Openness data Must Stskeeps 0%
9.11-05 Starting to work on a open sourcing queue Must Stskeeps 0%
9.11-06 Help out the SSU team to get them started Must Stskeeps 0%
9.11-07 Mer 0.17 release and facilitating Maemo on non-N900 OMAP3 boards (beagle, etc) Must Stskeeps 0%
9.11-08 No orphan pages and revise Wiki navigation Must dneary 0%
9.11-09 Integrate more minimae checks (around ten new checks) Must jeremiah 0%
9.11-10 Integrate ITP database with general package database Must jeremiah 0%
9.11-11 Install and test reprepro on new infrastructure Must jeremiah 0%
9.11-12 Brainstorm/improve Extras-testing Q&A Must VDVsx, jeremiah, lma 0%
9.09-10 Implement SSO sync-API endpoint for garage Should danielwilms 0%
9.10-13 Distribute 'Fixed In Fremantle' shirts to contributors that didn't make it to the Summit Should qgil 0%
9.10-14 Create a RFP (Request for Packaging) interface just like the ITP Should jeremiah 0%
9.10-15 Prepare a Bugday Should andre 0%
9.08-12 Improve reporting feed appearance on sprint page Could Ferenc 0% To liaise with Jaffa. I am happy to pass it on, November will be the month of the server move.
9.10-09 Prototype library.maemo.org Could dneary 0% No progress - vacation & wiki clean-up got in the way.
9.10-10 Add extra info fields from control files to interface - Changelog Could X-Fade 0%
9.11-16 Update Fremantle roadmap Could qgil 0%
9.11-17 Implement new UI for the application-downloader Could danielwilms, wazd 0%

Actions

None yet

Activity log

Latest activity report goes on top. Activity will be reported here, Qaiku #maemork channel (Atom feed) or talk.maemo.org.


Error: It's not possible to get http://pipes.yahoo.com/pipes/pipe.run?_id=mvdCJrB_3hGfIDijIDfpSg&_render=rss...