100Days/Sprint5

Contents

Sprint 5 planning

Tasks

Ongoing tasks carried here from the previous sprint + New tasks committed by their owners in the sprint meeting. They come from the tasks in the Backlog and the Proposals.

Completed Good progress Just standing Some help needed! Really stuck/delayed
Committed Task Owner  % Highlights
2008-06-10 Better extras categories and debtags Niels 50% Proposal drafted in wiki page, need to discuss on maemo-developers. (No progress will be made by me in Sprint4, need help!)
2008-07-22 Task:Using garage.maemo.org Ferenc 0%
2008-08-12 Better organization of bugs.maemo.org components Andre 30% Work on better organization of components in some products to fit better the scope of the corresponding Nokia developer teams, see bug 3562 - still drawing the big picture and trying to link all components between Maemo Bugzilla and internal bug tracker and its affiliated development teams. Hopefully done for Sprint5.
2008-08-12 Work on Bugzilla weekly summary functionality Karsten 20% Progressing slowly.
2008-08-12 Several smaller Bugzilla enhancements Karsten 70% See bug 1417, bug 2463, bug 3350 and some more, minor issues. Guided submission form pending, needs cleanup first.
2008-08-13 Plan for Task:Brainstorming new features Oskari 0% Specification needs to be added to wiki.
2008-08-13 Task:Community Council Dave DONE Election kicked off, announced. All that's left is to stimulate debate, and declare winners.
2008-09-02 Task:Fast Server Marcell 0%
2008-09-02 Task:Maemo_contributions to open source projects Quim 0%
2008-09-02 Task:Maemo_public_roadmapping_process Quim 0% I don't expect to have time to go through this in the current sprint. fwiw Fremantle roadmap to be shared, see "Announce the Fremantle plans and libraries changes" task below
2008-09-02 Document explaining the open source positioning and strategy of Nokia in Maemo Quim 50% Got base materials to work upon
2008-09-02 Explanation of the reasons why the closed source packages are closed Quim 10% Aim to provide general reasons but won't have time to detail package by package
2008-09-02 Task:ITt_Collaboration Henri 10% Started discussing the karma plugin Reggie
2008-09-02 High plan forTask:Improving maemo.org Dave 0%
2008-09-02 Summit program defined Quim DONE Remaining details to be healed themelves
2008-09-02 Maemo merchandising ready Jussi 90% 900 shirts and 700 lanyards purchased, expected around 10 Sep
2008-09-02 Marketing & coverage Quim 0% I would prefer someone else to coordinate this - I will help of course
2008-09-02 Summit social events Who? 0% Someone needs to take this one
2008-09-02 Announce the Fremantle plans and libraries changes Quim 40% Basic structure in place

Bugs in product Website

The bugs assigned in the last sprint meeting are marked as HIGH. The bugs proposed for the next sprint are marked as MEDIUM. Only product/component maintainers can change this status. Comment on a bug if you want to push it up. Check also those marked as EASYFIX.

What follows are the bugs that need special attention/progress.

For the record:

no bugzilla tickets were found
Warnings were generated during the execution of function
  1. Parameter columns=id, priority, severity, modified, product, status, summary, to is invalid using regex /^[\w,_+-~]*$/

Activity log

Latest activity report goes on top.

Monday 2008-09-08
  • Dave
    • End of last week: get election running, announce it on mailing lists, issue ballots, break web app & fix it. Tried to defuse Darius issue, didn't have a positive effect.
    • Today: Re-issue some voting tokens. Start working on proposal for website revamp.
  • Quim
    • Friday: Details on Summit schedule. Fremantle plans announcement.
    • Today: Fremantle plans announcement.
  • Niels
    • Today: Try to catch up on email and urgent matters after holiday.
Friday 2008-09-05
  • Bergie
    • Yesterday: Fixed Dave's broken voting commit, ran some voter counts
    • Today: Started ITT Karma API discussion with Reggie, fixed lost comments from application catalogue
  • Quim
    • Yesterday: Working on Fremantle plans announcement. Sorted out lightning sessions in Summit schedule and contacted Eric for final review.
    • Today: Close Summit schedule. Fremantle plans announcement
Thursday 2008-09-04
  • Quim
    • Yesterday: 100Days/Sprint5 page updated. Mail. OSiM related: invoices and ad.
    • Today: Planning OSiM DevSesh. Summit schedule.
Wednesday 2008-09-03
  • Rambo
    • Yesterday: Sprint5 meeting, explanatory and status mails about new servers
    • Today: Testing LB monitoring URL with new servers, set up to answer with IP as hostname as well
  • Bergie
    • Yesterday: Working on some Medium bugs, Sprint5 meeting
    • Today: Help Dave get elections running, getin in contact with Reggie from ITT
  • Quim
    • Yesterday: Scanned pending email in maemo.org lists. More email. Facilitated Sprint5 planning meeting. Minor tasks for OSiM organization: logos, bios, invoices.
    • Today: Update the 100Days/Sprint5 page reflecting agreements in the planning meeting. Organize my (many) committed tasks for this sprint. More mail.