100Days/Sprint4

(Bring over tasks from Sprint3)
(Added new Tasks for Karsten and me)
Line 32: Line 32:
|- style="background:Tomato"
|- style="background:Tomato"
| 2008-07-22 || [[Task:Using garage.maemo.org]] || Ferenc || 0% || Ran out of time in Sprint3.
| 2008-07-22 || [[Task:Using garage.maemo.org]] || Ferenc || 0% || Ran out of time in Sprint3.
 +
|-
 +
| 2008-08-12 || [[Task:Getting Nokia involved in bugs.maemo.org]] || Andre || 0% || Work on better organization of components in some products to fit better the scope of the corresponding Nokia developer teams, see [https://bugs.maemo.org/show_bug.cgi?id=3557 bug 3557]
 +
|-
 +
| 2008-08-12 || [https://bugs.maemo.org/show_bug.cgi?id=3553 Work on Bugzilla weekly summary functionality] || Karsten || 0% ||
 +
|-
 +
| 2008-08-12 || Several smaller Bugzilla enhancements || Karsten || 0% || see [https://bugs.maemo.org/show_bug.cgi?id=1417 bug 1417], [https://bugs.maemo.org/show_bug.cgi?id=2463 bug 2463], [https://bugs.maemo.org/show_bug.cgi?id=3350 bug 3350]
|}
|}

Revision as of 19:29, 12 August 2008

Contents

Sprint 4 planning

There will be an IRC review meeting of this sprint on Tuesday 2008/09/02 19:00 UTC.

Tasks

Ongoing tasks carried here from the previous sprint + New tasks committed by their owners in the sprint meeting. They come from the tasks accepted in the Backlog or (re)new(ed) proposals.

Completed Good progress Just standing Some help needed! Really stuck/delayed
Committed Task Owner  % Highlights
2008-05-10 Who's who in Maemo Dave 90% Awaiting deployment of new profile list to announce changes in profiles. Need to find a final home for the maintainer list
2008-06-10 Better extras categories and debtags Niels 50% Proposal drafted in wiki page, need to discuss on maemo-developers. (No progress will be made by me in Sprint4, need help!)
2008-06-10 Forum interface to mailing lists released Bergie 0% Beta to be made public for testing
2008-07-22 Task:Using garage.maemo.org Ferenc 0% Ran out of time in Sprint3.
2008-08-12 Task:Getting Nokia involved in bugs.maemo.org Andre 0% Work on better organization of components in some products to fit better the scope of the corresponding Nokia developer teams, see bug 3557
2008-08-12 Work on Bugzilla weekly summary functionality Karsten 0%
2008-08-12 Several smaller Bugzilla enhancements Karsten 0% see bug 1417, bug 2463, bug 3350

Bugs in product Website

The bugs assigned in the last sprint meeting are marked as HIGH. The bugs proposed for the next sprint are marked as MEDIUM. Only product/component maintainers can change this status. Comment on a bug if you want to push it up. Check also those marked as EASYFIX.

What follows are the bugs that need special attention/progress.

For the record (Bugs that will probably be brought over from Sprint 3):

no bugzilla tickets were found
Warnings were generated during the execution of function
  1. Parameter columns=id, priority, severity, modified, product, status, summary, to is invalid using regex /^[\w,_+-~]*$/

Proposed bugs for Sprint 4 (Medium priority):

no bugzilla tickets were found
Warnings were generated during the execution of function
  1. Parameter columns=id, priority, severity, modified, product, status, summary, to is invalid using regex /^[\w,_+-~]*$/

Activity log

Latest activity report goes on top.

Wednesday 2008-08-13

Tasks

To be committed in the sprint meeting from those listed in the Maemo.org backlog or Maemo.org proposals.