Maemo.org Sprints/November 08
November 2008 Sprint planning
- Planning meeting organized in the #maemo-meeting IRC channel on Tuesday 2008/11/04 at 20:00 UTC.
- Right after Maemo.org Sprints/October 08 review.
- Followed by Maemo.org Sprints/December 08.
Tasks
Ongoing tasks carried here from the previous sprint + New tasks committed by their owners in the sprint meeting. They come from the tasks in the Backlog and the Proposals.
Completed | Good progress | Just standing | Some help needed! | Really stuck/delayed |
Committed | Task | Owner | % | Highlights |
---|---|---|---|---|
2008-08-12 | Push Better organization of bugs.maemo.org components to 70% | Andre | 70% | Draft now available at Talk:Task:Getting_Nokia_involved_in_bugs.maemo.org#Draft_structure, still a few open questions left to solve/find out |
2008-09-02 | Task:Fast Server | Tero | 30% | Half-way there, we still need to upgrade to Ragnaroek |
2008-09-02 | ITT app catalog feeds | Henri | 0% | |
2008-09-30 | Who and how works on the maemo.org design | Dave | 50% | Process proposed, waiting for feedback and confirmation of roles. Dave Neary, Tim Samoff and Jaffa will work with INdT's designers to get a final design, before working on getting it implemented in Midgard. |
2008-09-30 | Propose a new structure for maemo.org/development | Dave | 30% | Proposal exists, I would like to wireframe some mock-ups. Layout will depend on the final layout of the front page, most likely. Waiting for INdT relationship & contacts to be clarified. |
2008-09-30 | Task:Reducing number of external repositories | Niels | 40% | Contacted most owners. Had a lot of positive responses, but need to gently push most of them again.. |
2008-09-30 | Define and publish first Feature Jar for the community and Nokia product managers | Andre | 80% | See this email - second iteration based on Quim's feedback planned for first week of November |
2008-09-30 | Task:Open Source Proof Points | Quim | 5% | Started preliminary discussion. |