Maemo.org Sprints/September 09
Contents |
[edit] September 2009 Sprint planning
- Planning meeting: Tuesday, 1st September 13:30 UTC in #maemo-meeting.
- Follows August 09. Precedes October 09.
- Main themes: September council election; October summit
[edit] Tasks
Ongoing tasks carried here from the previous sprint + New tasks committed by their owners in the sprint meeting. They come from the tasks in the Backlog and the Proposals.
Completed | Good progress | Just standing | Some help needed! | Really stuck/delayed |
Task ID | Task | Sprint priority | Owner | Percentage complete | Notes |
---|---|---|---|---|---|
9.08-01 | Get "Nokia patches" cleanly into Bugzilla 3.4 test install, dropping as many deltas as possible | Must | Ferenc | DONE | See my comments on the various patches |
9.08-04 | Integrate minimae into package promotion to get infrastructure & UI in place | Must | Jeremiah | 90% | |
9.08-06 | Produce Maemo Summit 2009 budget v0.99 | Must | qgil | DONE | It's done. I just didn't find the time to share with the council. What counts is that we allocated all the budget satisfying all the needs. |
9.08-08 | Co-ordinate summit council responsibilities | Must | timsamoff | 100% | Merchandising/accomodation etc:
|
9.04-05 | Implement new maemo.org layout and style - Bugzilla | Must | Andre | 80% | |
9.08-11 | Document & communicate packages interface to testers | Must | Jaffa | 0% | Not done. |
9.09-01 | Push packaging policy updates | Must | X-Fade | 40% | Make some changes, waiting for Daniel to pass it to Nokia internal team. |
9.09-02 | Run council election | Must | dneary | 100% | |
9.09-03 | Finalise summit community day schedule | Must | dneary, VDVsx, baloo | 100% | |
9.09-04 | Approve/reject all summit sponsorship requests | Must | Jaffa | 100% | |
9.08-10 | Draft quality guidelines for extras-testing to extras promotion | Should | qgil | 10% | Drafting at Extras-testing Quality_criteria + tmo discussion. |
9.06-09 | Vendor Hardware Repositories - decide on sub-tasks for next sprint | Should | Stskeeps | 100% | Got a single task for X-Fade to do. |
9.09-05 | Add source packages and repositories to packages interface | Should | X-Fade | 100% | DONE |
9.09-06 | Put Maemo 5 section for Downloads online | Should | X-Fade | 99% | Will announce before summit |
9.09-07 | Fremantle documentation priorities investigation | Should | dneary | 0% | |
9.06-14 | Plan for the OMAP2 acceleration drivers | Could | qgil | 15% | TI contact has resources ready. They are getting access to the source code from TI and maemo in order to start the work. Sadly not much real progress. Ask TI in the Summit. ;) |
9.08-12 | Improve reporting feed appearance on sprint page | Could | Ferenc | 0% | To liaise with Jaffa |
9.04-08 | ITP process/workflow around prototype | Could | Jeremiah | 90% | |
9.09-08 | Add extra info fields from control files to interface | Could | X-Fade | 100% | Added icon and bugtracker |
9.09-09 | Build a testing mirror of repos | Could | Jeremiah | 0% | |
9.09-10 | Implement SSO sync-API endpoint for garage | Could | danielwilms | 0% |
[edit] Actions
[edit] Activity log
Latest activity report goes on top. Activity will be reported here, Qaiku #maemork channel (Atom feed) or talk.maemo.org.
See latest sprint for activity
- This page was last modified on 4 May 2010, at 10:01.
- This page has been accessed 36,288 times.