Maemo.org Sprints/December 09
Contents |
[edit] December 2009 Sprint planning
- Planning meeting: Tuesday, 1st December 14:30 UTC in #maemo-meeting.
- Follows November 09. Precedes January 10.
[edit] Tasks
Ongoing tasks carried here from the previous sprint + New tasks committed by their owners in the sprint meeting. They come from the tasks in the Backlog and the Proposals.
Completed | Good progress | Just standing | Some help needed! | Really stuck/delayed |
Task ID | Task | Sprint priority | Owner | Percentage complete | Notes |
---|---|---|---|---|---|
9.08-12 | Improve reporting feed appearance on sprint page | Must | Ferenc | 100% | {Jaffa} Done - see below. {Ferenc} Many thanks Jaffa!! |
9.09-01 | Push packaging policy updates | Must | X-Fade, danielwilms | 60% | Unfortunately more changes needed than expected, not completed yet |
9.10-07 | Server migration | Must | Ferenc | 30% | Two servers have been moved completely. The SMTP switch over including the mailing list server are done. Next is switching maemo.org and garage. Linked to ISP move. |
9.11-01 | Refresh maemo.org intro | Must | qgil | 0% | See Talk thread and Josefdk wiki proposal |
9.11-02 | Maemo Greeters program | Must | texrat | 100% | Pilot started: http://talk.maemo.org/showthread.php?t=33968. Very quick engagement by members, better than expected. Ideas coming fast and furious! A Greeters page has been started by member smarsh and slowly being expanded: http://wiki.maemo.org/Greeters . Some refining left to be done; will create new subtask. |
9.11-03 | Get a decision on Developers should get karma based on the relevance of their software | Must | VDVsx | DONE | Discussion. Need to be implement and further discussed along with the other karma changes, remaining bits will be carry into the next sprint in a new task. |
9.11-04 | Openness data; web site containing the various status of openness of packages and components in the maemo OS | Must | Stskeeps | 99% | Almost done, will publish when polished. |
9.11-05 | Starting to work on a open sourcing queue | Must | Stskeeps | 70% | Edited Why_the_closed_packages and began blog series to improve open sourcing process. |
9.11-06 | Help out the SSU team to get them started | Must | Stskeeps | 70% | Spent time with TI drivers to get those proper and discussions about how in practice to implement a SSU. TI drivers now mostly work, waiting for TI to release a shrinkwrap package. Helped jeremiah bootstrap SSU repositories. |
9.11-07 | Mer 0.17 release and facilitating Maemo on non-N900 OMAP3 boards (beagle, etc) | Must | Stskeeps | 95% | Mer 0.17 release a bit delayed due to various technical issues. Beagle and Zoom2 ports work but got set back by the new SDK. |
9.11-08 | No orphaned pages and revise Wiki navigation | Must | dneary | 30% | See Wiki gardeners page for precise details, and Special:Lonelypages for progress. |
9.11-10 | Integrate ITP database with general package database | Must | jeremiah | 100% | Also changed the style somewhat so that it looks good on the N900 :) |
9.11-11 | Install and test reprepro on new infrastructure | Must | jeremiah | 100% | Installed reprepro and dependencies. Able to import packages manually as debs, automatically through inoticoming. Later I'll work with Ed and X-Fade tosee if I can pull in new packages via NFS to the builder. |
9.12-1 | Working bugzilla 3.4, migration path notes | Must | Andre, Karsten | 70% | Making progress, some lagging due to new infra (which is very good in the long run). |
9.12-2 | SSO: Testing/deployment user-management backend | Must | indeyets | 90% | Backend passes internal tests. Can create/get/edit users from command line client |
9.11-3 | Maemo event flyer (initial) | Must | texrat | 90% | Several drafts completed. Excellent feedback provided by Tim Samoff and Vaino Vallina. Continual progress made. Hope to have preliminary flyers for distribution at local (Dallas) linux user event 9 January 2010. |
9.11-4 | CLI application icon for HAM | Must | timsamoff | 80% |
|
9.09-10 | Implement SSO sync-API endpoint for garage | Should | danielwilms | 80% | implemented new server instance for midgard account-sync, cas change from ldap to MySQL, certificates in place for endpoint-sync |
9.10-13 | Distribute 'Fixed In Fremantle' shirts to contributors that didn't make it to the Summit | Should | qgil | 0% | http://wiki.maemo.org/FIXED_in_Fremantle_Hall_of_Fame started |
9.10-14 | Create a RFP (Request for Packaging) interface just like the ITP | Should | jeremiah | 80% | |
9.10-15 | Prepare a Bugday | Should | andre | 100% | Updated & restructured Bugsquad wikipage. 2009-11-30: Greasemonkey script published; asked for defining a Bugday date (Doodle) on the community mailing list. 2009-12-02: Set up Bugday wikisubpage, split "Potential tasks" into "Recurring" and "Others" and move it to its own subpage, and link to it from Bugdays and Triage Guide. 2009-12-07: Announce final date everywhere (planet, forum, mailing lists) & introduce wazd's cool Bugsquad logo. Hence DONE. 2009-12-15: Have our first Bugday. Bonus points for volunteers or Andre in case of providing a video screencast that introduces new people into triaging. See Ubuntu example. |
9.12-5 | BMO: maemo.org custom features backport, Nokia patches | Should | Andre, Karsten | 0% | |
9.12-6 | SSO: midgard syncing with usermanagement-server | Should | indeyets | 30% | |
9.10-09 | Prototype library.maemo.org | Could | dneary | 0% | No progress - vacation & wiki clean-up got in the way. |
9.10-10 | Add extra info fields from control files to interface - Changelog | Could | X-Fade | 0% | |
9.11-16 | Update Fremantle roadmap | Could | qgil | 0% | |
9.11-17 | Implement new UI for the application-downloader | Could | danielwilms, wazd | 60% | changes in REST-API done, now completing UI changes |
9.12-7 | BMO: CSS, maemo.org style | Should | Andre, Karsten | 0% |
[edit] Actions
None yet
[edit] Activity log
Latest activity report goes on top. Activity will be reported here, Qaiku #maemork channel (Atom feed) or talk.maemo.org.
See latest sprint for activity